The Jamalpur-Bhagalpur rail section is set for a major infrastructure overhaul with the construction of a third tunnel and the laying of new railway lines. This project aims to increase train speeds to 130 km/h and improve travel efficiency in Bihar. Eastern Railway has already started the survey and land acquisition process to ensure the project stays on track for its scheduled completion.
ℹ️: Ghaziabad-Delhi Rail Update: Infrastructure upgrades and RRTS expansion to reduce travel time।
Key features of the Jamalpur-Bhagalpur expansion project
The new project focuses on separating passenger and freight traffic to reduce delays. The third tunnel will be designed significantly wider than the existing ones to facilitate smooth freight movement. This infrastructure boost will transform the corridor into one of the fastest routes in the region.
| Feature | Details |
|---|---|
| Project Cost | ₹1094.53 crore |
| New Line Length | 52.81 km |
| Target Speed | 130 km/h |
| Current Capacity | ~200 trains daily |
| Safety Measure | W-beam metal fencing |
Project timeline and official status
The construction work for the third tunnel and additional lines is expected to begin by the end of 2026. According to official reports, the third and fourth lines will be ready by 2028, while the entire project including the tunnel will reach completion by July 2030. Revenue and Forest departments are currently marking land ranging from 50 to 82 feet for acquisition.
- Survey work for the third tunnel is currently focused on the southern part of the existing second tunnel.
- Five level crossings between Jamalpur and Bhagalpur will be replaced by Limited Height Subways.
- The project will help in segregating freight traffic, allowing passenger trains to run on time.
- Approximately 200 houses and private land are under consideration for the land acquisition process.