Bandikui Update: Dhauli Gumti railway level crossing closed after new overbridge opening

The Dhauli Gumti railway level crossing on Baswa Road in Bandikui, Dausa, is now permanently closed. This move comes after the official opening of a new railway overbridge (ROB) which will end the long wait for local commuters. Chief Minister Bhajanlal Sharma inaugurated the bridge on April 12, 2026.

What are the details of the new Dhauli Gumti overbridge?

The new overbridge is 980 meters long and was built to solve the problem of traffic jams at the level crossing. The project was first approved in 2015-16, but it took about 10 years to complete. Before opening it to the public, the authorities conducted a load test using eight dumpers with a total weight of 220 tons between March 30 and April 1, 2026.

HelloRail की हर खबर सबसे पहलेJoin Channel

What was the cost and impact of the project?

The construction cost of the overbridge was approximately ₹35 crore, which was higher than the original estimate of ₹28 crore. This project was pushed for completion by MLA Bhagchand Tankda to help the residents of the area. The bridge is expected to remove the long waiting times that people faced daily at the railway gate.

Feature Details
Inauguration Date April 12, 2026
Bridge Length 980 Meters
Total Cost Approx ₹35 Crore
Inaugurated By CM Bhajanlal Sharma
Load Test Weight 220 Tons

What is the next plan for Bandikui railway infrastructure?

Chief Minister Bhajanlal Sharma announced that another overbridge will be built at Agra Phatak in Bandikui. The railway department has already given approval for this new project. The estimated cost for the Agra Phatak overbridge is ₹60 crore.

Frequently Asked Questions (FAQs)

When was the Dhauli Gumti overbridge opened?

The overbridge was officially inaugurated by Chief Minister Bhajanlal Sharma on April 12, 2026.

What is the cost of the new overbridge project?

The project was completed at a cost of approximately ₹35 crore, increasing from the initial estimate of ₹28 crore.

{“@context”: “https://schema.org”, “@type”: “FAQPage”, “mainEntity”: [{“@type”: “Question”, “name”: “When was the Dhauli Gumti overbridge opened?”, “acceptedAnswer”: {“@type”: “Answer”, “text”: “The overbridge was officially inaugurated by Chief Minister Bhajanlal Sharma on April 12, 2026.”}}, {“@type”: “Question”, “name”: “What is the cost of the new overbridge project?”, “acceptedAnswer”: {“@type”: “Answer”, “text”: “The project was completed at a cost of approximately ₹35 crore, increasing from the initial estimate of ₹28 crore.”}}]}