Amrit Bharat Scheme: Rajasthan’s 146-year-old Beawar station gets a modern makeover at ₹15.55 crore

Kush Singh12 April 20261 min read1 viewDevelopment
Amrit Bharat Scheme: Rajasthan’s 146-year-old Beawar station gets a modern makeover at ₹15.55 crore

Beawar railway station in Rajasthan is getting a major facelift after nearly 146 years of its establishment. This redevelopment project is part of the Amrit Bharat Station Scheme with an estimated cost of ₹15.55 crore. The initiative aims to modernize the station building while preserving its historical essence and improving passenger comfort.

ℹ: Indian Railways to install modern composite sleepers and AI technology for safer train journeys

What are the new features at Beawar railway station?

HelloRail की हर खबर सबसे पहलेJoin Channel

The project includes the construction of a new station building and a second entry point for better access towards Mill Colony. A large circulating area of 10,000 square meters is being developed to manage traffic flow efficiently. Passengers will soon have access to modern waiting halls, including VIP lounges, baby feeding rooms, and pay-and-use toilets.

  • A 12-meter wide foot overbridge with lift facilities is being installed.
  • Modern platform shelters and improved signage for better navigation.
  • Specific facilities for Divyangjan and new water booths.
  • A 4,000 square meter new station building area.

Current status and technical upgrades of the project

Work is currently in its concluding phases, focusing on the completion of the foot overbridge and final touches to the circulating area. Most internal works, such as painting, booking windows, and platform improvements, are already finished. Officials from the Ajmer Division have directed the team to accelerate the remaining tasks to ensure the station is fully operational with its new look shortly.

Project Detail Information
Total Estimated Cost ₹15.55 Crore
Historical Age 146 Years (Established 1880)
Circulating Area 10,000 Square Meters
Foot Overbridge Width 12 Meters
Completion Status Over 80% as per latest review