Bhanupalli-Beri Rail: 5 Bridges Nearly Ready Amid Legal Battles
Construction of the Bhanupalli-Beri railway line hits milestones with bridges nearly complete, despite legal hurdles and local protests.

The construction of the Bhanupalli-Bilaspur-Beri railway line has reached a significant milestone, with five major railway bridges up to Dharot nearing completion. In a major boost to the project, track linking has already been successfully finished on the second bridge, signaling steady progress in the mountainous terrain.
Connecting Himachal Pradesh to the National Grid
This ambitious 63-kilometer broad-gauge project is designed to integrate Himachal Pradesh into the national railway network. The project is divided into two key phases: a 52-kilometer stretch from Bhanupalli to Bilaspur and an 11-kilometer section from Bilaspur to Beri. Once fully operational, the line is expected to provide a massive boost to regional tourism, trade, industry, and the overall economy of the Bilaspur region.
Infrastructure and Tunnel Milestones
The engineering feat is well underway, particularly in the 52-kilometer Bhanupalli-Bilaspur section. Out of the 16 tunnels required for this stretch, 15 have already been completed. Additionally, track laying is progressing well, with 8 kilometers of track successfully laid as of July 2026.
Legal Hurdles and Financial Challenges
Despite the physical advancements, the project is navigating complex legal and financial waters. On September 30, 2026, the Himachal Pradesh High Court declared previous land acquisition notifications illegal and invalid, citing a lack of genuine reasons for delays in official files. This decision terminated the preliminary notification that had been in place since March 2023.
The funding for the project is a joint effort, with the Central Government contributing 75 percent and the State Government covering 25 percent. The state is also responsible for land acquisition costs, which exceed 70 crore rupees. While 231 of the required 232 hectares of land have been acquired in Himachal Pradesh, the state's financial contributions have faced delays. As of December 25, 2025, the Himachal Pradesh government had paid 847 crore rupees out of its total share of 2,711 crore rupees.
Local Disputes and Security Measures
Construction has also faced interruptions due to local grievances and security concerns. At the Nilah site, unidentified individuals allegedly harassed workers and threatened to burn machinery on November 27. The following day, November 28, villagers gathered at the Dabhat Khadd site to demand repairs to approach roads and related construction works.
In response to these disruptions, Rail Vikas Nigam Limited (RVNL) has formally requested police security to protect the site and personnel. Officials anticipate that work at these specific locations will resume within three to four days.