Railway Minister Ashwini Vaishnaw visited Ahmedabad on Saturday, July 4, 2026, to check the progress of the Mumbai-Ahmedabad Bullet Train project. He inspected the construction at the Ahmedabad Bullet Train Station located at Kalupur. During the visit, the Minister reviewed the work and interacted with the staff and laborers to encourage them.
ℹ: Rajasthan Rail Update: Churu–Ratangarh rail line doubling project dedicated to the nation।
What are the key updates on the project timeline
The Railway Minister shared that about 80% of the bullet train work in Gujarat is already finished. The government plans to open the first section of the high-speed rail between Surat and Bilimora in 2027. The entire project from Mumbai to Ahmedabad is expected to be completed in different phases by 2029.
How will the Ahmedabad station work for passengers
The Ahmedabad station is being built as a multi-modal hub. This means passengers can easily switch between the Bullet Train, Metro, city buses, and regular Indian Railways trains at one single complex. The tracks in the Ahmedabad city area will be elevated, reaching an average height of around 100 feet to manage city traffic.
Other important project details
| Feature | Details |
|---|---|
| Gujarat Work Progress | Approximately 80% complete |
| First Section Opening | Surat to Bilimora by 2027 |
| Full Project Completion | Expected by 2029 |
| Station Type | Multi-modal integration (Bus, Metro, Rail) |
| Track Height in City | Average 100 feet elevated |
Frequently Asked Questions (FAQs)
When will the first part of the Bullet Train start?
The first section of the project between Surat and Bilimora is targeted to open in 2027.
What is special about the Ahmedabad Bullet Train station?
It will be a multi-modal hub connecting Bullet Train, Metro, buses, and regular trains in one complex for easy passenger movement.