Dholpur-Garhi Sandra Line: High-Speed Trial Hits 121 km/h!

CRS completes high-speed trial on the new Dholpur-Garhi Sandra section. Regular train services expected by late 2026.

Kush Singh25 November 20262 min read0 viewsDevelopment
Dholpur-Garhi Sandra Line: High-Speed Trial Hits 121 km/h!

The wait for improved rail connectivity in the region is nearing its end. On October 31, 2026, the North Eastern Circle Commissioner of Railway Safety, E. Srinivas, successfully conducted a comprehensive inspection of the newly constructed Dholpur-Garhi Sandra railway line.

High-Speed Testing and Safety Audit

To ensure the new infrastructure meets all safety standards, a special train was deployed to conduct a high-speed trial run. The train reached a velocity of 121 km/h on the newly laid 19.8-kilometer broad-gauge section. This rigorous assessment was not limited to speed alone; the inspection team also performed a detailed motor trolley survey and conducted exhaustive checks on:

HelloRail की हर खबर सबसे पहलेJoin Channel
  • Signaling infrastructure and operational arrangements.
  • The overall integrity of the track network.
  • Safety protocols for upcoming commercial operations.

The inspection was attended by high-ranking officials, including Chief Administrative Officer Ajit Singh Yadav and Agra Divisional Railway Manager Gagan Goyal.

A Major Step in Regional Connectivity

This 19.8-kilometer stretch is a critical piece of the much larger 69-kilometer Dholpur-Sirmuttra gauge conversion project. This project serves as a vital segment of the broader Dholpur-Sirmuttra-Gangapur City corridor, designed to enhance movement across the region.

The scale of this infrastructure undertaking is backed by significant financial investment:

The entire project was sanctioned with a total budget of 747 crore rupees.

Financial records indicate that 504 crore rupees had been spent as of March 2026, with an additional 275 crore rupees allocated for the 2026-27 financial year to push the project toward completion.

Work Completed and Future Timelines

The completed 18-kilometer portion of the Dholpur-Garhi Sandra section includes the construction of major bridges, road underbridges (RUBs), station buildings, and essential track linking. Furthermore, the project has successfully managed the acquisition of 24 out of the required 30 hectares of land.

For passengers and commuters, the timeline for service is looking promising. Preparations are currently underway to begin regular train operations on the Dholpur-Garhi Sandra and Bari sections, which is expected to happen between November and December 2026. The full Dholpur-Sarmathura broad gauge line is targeted for completion by June 2027, with subsequent phases planned to extend the line toward the Karauli district.