Gorakhpur is seeing several railway overbridge projects to reduce traffic congestion. Recent activities include the installation of girders and planned railway blocks to ensure construction progress. The North Eastern Railway and local administrations are working to complete these projects to ease travel for the public.

What is the status of the Gorakhnath Overbridge projects

The old Gorakhnath overbridge underwent maintenance from May 17, 2026, with a focus on replacing expansion joints. Simultaneously, a new two-lane railway overbridge is being built with a budget of ₹127.87 crore. This new bridge uses bow string girder technology and is expected to be completed by the end of December 2025. It will feature safety covers and advanced lighting for night travel.

HelloRail की हर खबर सबसे पहलेJoin Channel

Details on Foot Overbridge and Cantt Railway Crossing

A mega block was implemented at Gorakhpur Junction from May 29 to early June 2026 for the construction of a Foot Overbridge (FOB). The railway administration aims to finish this FOB by Diwali. Additionally, a new Y-shaped two-lane overbridge at Railway Crossing 157A near Gorakhpur Cantt station is planned. This project will cost ₹69 crore, and the agency selection process was finalized in December 2025.

Key Infrastructure Project Details

Project Name Cost/Detail Expected Completion/Status
New Gorakhnath ROB ₹127.87 Crore December 2025
Cantt Crossing ROB ₹69 Crore Construction starting 2026
Gorakhpur FOB Mega Block taken By Diwali 2026
Nakha Overbridge Inaugurated January 2026

Frequently Asked Questions (FAQs)

When will the new Gorakhnath Overbridge be ready?

The new two-lane railway overbridge in the Gorakhnath area is expected to be completed by the end of December 2025.

What is the cost of the Cantt Railway Crossing overbridge?

The Y-shaped two-lane overbridge at Railway Crossing 157A near Gorakhpur Cantt is estimated to cost ₹69 crore.