DRM Inspects Hapur Railway Station Redevelopment

DRM Vinita Srivastava inspects Hapur Railway Station redevelopment and orders urgent repairs for construction flaws under the Amrit Bharat Scheme.

Kush Singh29 October 20261 min read0 viewsDevelopment
DRM Inspects Hapur Railway Station Redevelopment

The Divisional Railway Manager (DRM) of the Moradabad division, Vinita Srivastava, conducted a formal inspection of the ongoing Hapur Railway Station redevelopment on Wednesday, October 28, 2026. The visit focused on the progress of renovation and beautification works being carried out under the central government's Amrit Bharat Station Scheme.

The inspection, which commenced at approximately 5:00 PM, was intended to review the status of ongoing construction. However, the DRM expressed significant dissatisfaction regarding the quality and current state of the project.

Critical Construction Flaws Identified

HelloRail की हर खबर सबसे पहलेJoin Channel

During her walkthrough of the station, several critical deficiencies were highlighted that require immediate attention from the concerned departments:

  • Exposed electrical wiring that poses potential safety concerns.
  • Issues regarding the descent of the Road Over Bridge (ROB).
  • Unsatisfactory levels of cleanliness across the station premises.
  • The incomplete status of the boundary wall.

Directives for Passenger Convenience

To address these shortcomings, the DRM issued formal directives to the railway staff to expedite all necessary corrective measures. Beyond structural repairs, she emphasized the need for superior passenger management and smoother transit. Her specific instructions included:

  • The separation of entry and exit routes to prevent congestion.
  • The establishment of alternative routes for heavy vehicles.
  • The finalization and activation of parking facilities to ensure improved convenience for travelers.

Senior Officials in Attendance

The inspection was attended by several senior officials and technical experts, including:

  • Mahesh Yadav (Senior Divisional Commercial Manager)
  • Ramkesh Meena (Station Superintendent)
  • Rohit Gupta (CMI)
  • Vineet Sharma (CIT)
  • Haripal Meena (Chief Sanitation Inspector)

Various members of the technical team were also present to receive direct instructions regarding the required site improvements.