Indore Railway Station: Redevelopment work speeds up, new facilities for 24-coach trains and elderly passengers

Kush Singh7 April 20262 min read3 viewsDevelopment
Indore Railway Station: Redevelopment work speeds up, new facilities for 24-coach trains and elderly passengers

Indore Railway Station is undergoing a massive transformation under the Amrit Bharat Station Scheme to provide world-class facilities to travelers. With an estimated budget of 412 crore, the project aims to turn the station into a high-tech travel hub similar to an airport. The ongoing work focuses on lengthening all platforms to accommodate 24-coach trains and ensuring that senior citizens face no difficulty while boarding or deboarding.

👉: Railway safety boost: Indian Railways approves ₹1,364 crore plan for Kavach 4.0 and signaling upgrades

Key Modern Facilities and Infrastructure Upgrades

HelloRail की हर खबर सबसे पहलेJoin Channel

The redevelopment plan includes several advanced features designed for the comfort of thousands of daily commuters. The new station building will be a seven-story structure equipped with modern amenities to handle increasing passenger traffic over the next 50 years. Local authorities and railway engineers are closely monitoring the quality of work to meet the 2027 completion deadline for the first phase.

  • Installation of 26 lifts and 17 escalators across the station
  • Development of a world-class waiting area and executive lounges
  • Air-conditioned waiting rooms and dedicated business meeting halls
  • Direct connectivity to the Indore Metro through a new skywalk system
  • Special provisions for Divyangjan and senior citizens at all touchpoints

Project Timeline and Current Construction Status

The redevelopment project has seen significant progress with the commencement of basement and parcel building construction on March 27, 2026. Member of Parliament Shankar Lalwani recently inspected the site to ensure the project stays on track. The Ahmedabad-based Monte Carlo company is executing the work under the supervision of Western Railway engineers. Once completed, the station is expected to handle more than one lakh passengers every day comfortably.

Project Component Details
Estimated Cost 412 Crore Rupees
Target Completion Phase 1 by 2027
Number of Lifts 26
Number of Escalators 17
Main Contractor Monte Carlo Company
Building Height 7 Floors