Kanpur Elevated Railway Track: PWD hands over 90% land to Railways, construction to start soon

Kush Singh30 April 20262 min read0 viewsDevelopment
Kanpur Elevated Railway Track: PWD hands over 90% land to Railways, construction to start soon

The Mandana-Anwarganj elevated railway track project in Kanpur has reached a major milestone. The Public Works Department (PWD) has handed over 90% of the required land to the Indian Railways. This project aims to remove traffic congestion at 18 railway crossings on GT Road, benefiting over 20 lakh people.

What is the current status of land acquisition?

Out of the total 22,306 square meters of land required, PWD has already transferred 90% to the railway authorities. PWD Executive Engineer Anup Mishra stated that the remaining 10% of land, including some areas near IIT Kanpur and Mandana, will be handed over by May 15. The total budget for land acquisition was reduced to approximately ₹20 crore as most of the land was already under government records.

HelloRail की हर खबर सबसे पहलेJoin Channel

Project details and key highlights

The project involves building a 15.51 km elevated track with an estimated cost of ₹1115 crore. The Ministry of Railways has already finalized the tender and assigned a private company for construction. A new railway station named after Bharat Ratna Atal Bihari Vajpayee will be built in front of Chhatrapati Shahuji Maharaj University, while Rawatpur and Kalyanpur stations will be closed.

Feature Details
Total Length 15.51 Kilometers
Estimated Cost ₹1115 Crore
Land Handed Over 90% (Remaining by May 15)
Target Completion 2027
Impact Relief for 20 lakh people from 18 crossings

When will the construction begin?

With the tender finalized and land acquisition nearly complete, construction is expected to start by the end of May. North Eastern Railway SSE Abhishek confirmed that there are no longer any hurdles to begin the work. The government has already sent a letter to the Prime Minister for the foundation stone laying ceremony.

Frequently Asked Questions (FAQs)

How will the Mandana-Anwarganj project help Kanpur residents?

The 15.51 km elevated track will eliminate 18 railway crossings on GT Road, providing traffic relief to more than 20 lakh people.

Which stations will be affected by this project?

A new station named after Atal Bihari Vajpayee will be created, while the existing Rawatpur and Kalyanpur stations are planned to be closed.

{“@context”: “https://schema.org”, “@type”: “FAQPage”, “mainEntity”: [{“@type”: “Question”, “name”: “How will the Mandana-Anwarganj project help Kanpur residents?”, “acceptedAnswer”: {“@type”: “Answer”, “text”: “The 15.51 km elevated track will eliminate 18 railway crossings on GT Road, providing traffic relief to more than 20 lakh people.”}}, {“@type”: “Question”, “name”: “Which stations will be affected by this project?”, “acceptedAnswer”: {“@type”: “Answer”, “text”: “A new station named after Atal Bihari Vajpayee will be created, while the existing Rawatpur and Kalyanpur stations are planned to be closed.”}}]}