Katni-Singrauli Rail Project: Third and fourth lines to be built for new high capacity freight corridor

Kush Singh27 May 20262 min read2 viewsDevelopment
Katni-Singrauli Rail Project: Third and fourth lines to be built for new high capacity freight corridor

Indian Railways has started a mega project to build a new high capacity freight corridor between Katni and Singrauli. This project is declared as a Special Railway Project and will focus on improving the movement of goods in Central India. The project aims to speed up the transport of coal and cement while reducing delays for other trains.

What are the key details of the Katni-Singrauli corridor project

The project involves the development of third and fourth rail lines over a corridor length of 264.070 kilometers. The total track development will cover approximately 578.675 kilometers with an estimated cost of 6779.87 crore rupees. The government has set a target to complete this work within 4 years.

Feature Details
Proposed Max Speed 130 kmph
Districts Covered Katni, Umaria, Shahdol, Sidhi, Singrauli
Additional Freight Trains 19 per day
New Passenger Trains 6 per day
Technical Features Long haul loops, High capacity signaling, Modern yards
HelloRail की हर खबर सबसे पहलेJoin Channel

How will this project benefit the region and industries

This new corridor will directly help the coal and cement industries by providing faster connectivity. It will lower the logistics costs for businesses and reduce the number of trucks on highways, which will lead to less pollution and lower diesel use. Additionally, the construction and operation of this corridor will create new local employment opportunities in the five covered districts.

Currently, the survey work is ongoing. The railway authorities are speeding up the land acquisition and approval processes to ensure the project stays on track.

Frequently Asked Questions (FAQs)

What is the total cost and timeline of the Katni-Singrauli project?

The project cost is approximately 6779.87 crore rupees and the target duration for completion is 4 years.

Which districts will benefit from this new rail corridor?

The corridor will pass through Katni, Umaria, Shahdol, Sidhi, and Singrauli districts.