Khalilabad-Bansi Rail Project: Land dispute for Malorna overbridge to be resolved soon

Kush Singh22 April 20261 min read0 viewsDevelopment
Khalilabad-Bansi Rail Project: Land dispute for Malorna overbridge to be resolved soon

The construction of the railway overbridge at Malorna on the Basti Highway is expected to speed up soon. This bridge is a key part of the Khalilabad-Bansi rail project. The district administration of Sant Kabir Nagar is now taking active steps to resolve a land dispute that has stalled the work for some time.

📰: Berhampur Railway Station: Redevelopment project worth 300 crore approved, 4 new platforms to be added

Why was the Malorna overbridge work stopped?

HelloRail की हर खबर सबसे पहलेJoin Channel

The construction was stuck due to a dispute over 1700 meters of land. Some local farmers claimed ownership of this land and demanded compensation, with some even filing petitions in court. Initially, the NHAI claimed ownership of the land but later withdrew its claim from some parts, which increased the conflict between the farmers and authorities.

What is the current status and next steps?

District Magistrate Alok Kumar has directed the Additional District Magistrate to call a meeting with Railway and Forest Department officials. This meeting aims to settle the land issues so the Railway can take possession and start construction without any hurdles. Site Incharge Sattar Ali mentioned that the service road work would have progressed further if the land matter was cleared.

Key details of the Khalilabad-Bansi Rail Project

Feature Details
Total Project Cost ₹4939.78 crore (Approved Oct 2018)
First Phase Khalilabad to Bansi (54 km)
Completion Target End of 2026
Current Work Underpass completed at Malorna, soil filling in progress
Executing Agency ZEPW Infra Private Limited