Lakhimpur Kheri: Ballast laying work causes delays on Mailani-Daliganj route

Kush Singh28 April 20262 min read1 viewNews
Lakhimpur Kheri: Ballast laying work causes delays on Mailani-Daliganj route

Railway passengers on the Mailani-Daliganj route faced significant delays on Tuesday, April 28, 2026. The disruption happened due to ballast laying work on the Mailani-Bankeganj section. This work was necessary to strengthen the track and improve water flow after cleaning the stones and dirt using an FRM machine.

ℹ: South Coastal Railway Zone: New railway zone to become operational from June 1 2026

Which trains were affected by the track work?

HelloRail की हर खबर सबसे पहलेJoin Channel

The ballast laying work led to delays for several passenger trains. The impact was felt most by those traveling between Mailani, Daliganj, and Pilibhit. Passengers faced difficulties due to the delays during the summer heat.

Train Number Train Name Delay/Status
55083 Mailani-Daliganj Passenger Departed Mailani at 2:15 PM (approx 2.25 hours late)
55086 Gomtinagar-Pilibhit Passenger Departed Mailani 2 hours late
55084 Daliganj-Mailani Passenger Arrived at Mailani at 3:15 PM (approx 2 hours late)

Why was the railway block taken?

Railway authorities took a block on the line to lay new ballast (gravel) on the tracks. Before this, the tracks were cleaned of soil, dust, and dirt using an FRM machine. This process is done to ensure the track remains strong and water does not accumulate on the rails.

Frequently Asked Questions (FAQs)

Why were trains delayed on the Mailani-Bankeganj section?

Trains were delayed on April 28, 2026, because railway authorities took a block to lay ballast (gravel) on the track to strengthen it.

Which specific trains were most affected by the delay?

Train 55083 (Mailani-Daliganj), Train 55086 (Gomtinagar-Pilibhit), and Train 55084 (Daliganj-Mailani) all experienced delays of approximately 2 hours.

{“@context”: “https://schema.org”, “@type”: “FAQPage”, “mainEntity”: [{“@type”: “Question”, “name”: “Why were trains delayed on the Mailani-Bankeganj section?”, “acceptedAnswer”: {“@type”: “Answer”, “text”: “Trains were delayed on April 28, 2026, because railway authorities took a block to lay ballast (gravel) on the track to strengthen it.”}}, {“@type”: “Question”, “name”: “Which specific trains were most affected by the delay?”, “acceptedAnswer”: {“@type”: “Answer”, “text”: “Train 55083 (Mailani-Daliganj), Train 55086 (Gomtinagar-Pilibhit), and Train 55084 (Daliganj-Mailani) all experienced delays of approximately 2 hours.”}}]}