Sanganer Railway Station in Jaipur is undergoing a major upgrade to transform its 103-year-old heritage design into a high-tech facility. The North Western Railway is investing 107.9 crore rupees into this project. Work has already started on the ground and the railway administration aims to complete everything by March 2028. This redevelopment follows the modernization of other key stations in the city like Jaipur Junction and Gandhinagar.
What modern facilities are being developed at the station?
The redevelopment plan includes a massive station building and a separate second entry to manage the crowd. Passengers will see a blend of Rajasthani culture and modern technology in the station architecture. New high-level platforms and a modern ticketing system will be established to handle the increasing number of travelers.
- Station Buildings: A main building of 3800 square meters and a second entry of 600 square meters.
- Passenger Movement: Installation of 4 lifts and 6 escalators for easy access.
- Platform Upgrades: Four high-level platforms connected by a 6-meter wide underpass and footover bridge.
- Safety Systems: Modern electronic interlocking for secure train operations.
Project timeline and expected local benefits
The project was initially announced under the Amrit Bharat Station Scheme but faced delays due to the Bisalpur water pipeline passing through the premises. After shifting the design, the North Western Railway has now started the work. This modernization will benefit residents of Mansarovar, Sanganer, and Tonk Road by providing better connectivity and a dedicated cargo complex for local industries.
| Feature | Project Detail |
|---|---|
| Total Budget | 107.9 Crore Rupees |
| Target Completion | March 2028 |
| Number of Tracks | Increased to 4 or 5 lines |
| Design Theme | Heritage and Rajasthani Culture |
| Special Facility | New Cargo Complex for local industries |