North Western Railway has modified the Detailed Project Report for the Bilara railway section extension. A new route has been finalized which includes the construction of a new station near Banganga. The project is currently awaiting financial approval from the Railway Ministry after the successful completion of the feasibility study in previous years.

What is the cost and route of the Bilara-Ras rail project?

The new broad-gauge line will connect Bilara to Ras through Jaitaran, Nimbol, and Tookda. The total cost for this infrastructure development is estimated at 850 crore rupees. Land acquisition for the tracks has already begun to ensure the project stays on schedule. North Western Railway officials have confirmed that this route change is a strategic move to improve regional connectivity in Rajasthan.

What are the major benefits for travelers and industries?

The most significant impact of this project is the reduction in travel distance between Beawar and Jodhpur. The journey will be shortened from 191 kilometers to 133 kilometers, saving passengers about one hour of travel time. Additionally, this line will support the transport of limestone, granite, and cement from local industries and assist in strategic military movements. The project is seen as a major boost for the local economy and regional development.

Feature Project Details
Estimated Cost 850 Crore Rupees
Distance Reduction 58 Kilometers
Time Saved Approximately 1 Hour
New Station Near Banganga
Key Industries Limestone, Granite, Cement
Total Length (New) 133 Kilometers