Rajendra Bridge Mega Block: 338 Trains Cancelled in Bihar

Rail passengers are facing major disruptions due to Rajendra Bridge train cancellations and diversions caused by a massive mega block. The disruption, which began on September 21, 2026, is expected to persist until October 4, 2026, causing widespread chaos for commuters across Bihar.
Massive Impact on Train Schedules
The ongoing construction work has heavily impacted the rail network, with official reports indicating that over 800 train services have been affected in total. The scale of the disruption is significant, with daily changes including:
- Cancellations: Between 35 and 51 trains are being cancelled each day.
- Diversions: Between 33 and 47 trains are having their routes altered to bypass the block zone.
The Danapur Railway Division is at the center of this disruption, with many trains being short-terminated before they reach their scheduled destinations.
Why is the Rajendra Bridge Mega Block happening?
The block is a necessary step for the integration of the newly constructed double-line rail bridge. This critical infrastructure project is designed to enhance connectivity between Dinkar Gram Simaria and Barauni.
To connect this new bridge to the existing main network, railway engineers must perform essential pre-non-interlocking and non-interlocking works. These technical procedures are vital to ensure the safety and seamless operation of the new line once it is fully operational.
Key Routes and Stations Affected
The disruption is not localized to a single area but spans several major routes and hubs, particularly affecting the Kolkata-Howrah corridor. Major locations experiencing heavy impact include:
- Major Cities & Hubs: Saharsa, Patna, Mokama, Barauni, Kiul, Jamalpur, Ara, Pataliputra, Muzaffarpur, Bhagalpur, and Sahibganj.
- Critical Station Zones: Mokama, Hathidah, Rampur Dumra, Tall Junction, and Dinkar Gram Simaria.
Railway officials have issued an advisory urging all passengers to verify the current status of their specific trains via official channels before starting their journey.
Normal train operations are expected to resume on October 5, 2026, once the operational integration of the new double-line bridge is successfully completed.