Rohtak Junction: New Foot Overbridge Construction Gains Speed!
Construction of a new foot overbridge at Rohtak Junction is accelerating to include escalators for better passenger mobility.

The landscape of Rohtak Junction is set for a major transformation as the construction of its new foot overbridge (FOB) enters an accelerated phase. This critical infrastructure project is being fast-tracked to enhance the commuting experience for thousands of passengers passing through the station every day.
Escalators to Boost Passenger Mobility
One of the most significant features of this new foot overbridge is its design, which is specifically engineered to facilitate the installation of escalators. By integrating these modern amenities, the railway aims to provide seamless mobility within the station premises. This upgrade will be a massive relief for elderly travelers, passengers carrying heavy luggage, and those with limited mobility, allowing them to navigate between platforms with ease.
Strategic Traffic Blocks for Safe Engineering
Assembling massive iron girders across active railway tracks is a complex and high-stakes task. To manage this safely, the railway administration has implemented a daily 'Special Power and Traffic Block.'
- Duration: Each block lasts between 30 minutes to one hour.
- Timing: Blocks are strictly scheduled during non-peak hours to prevent disruption to regular train services.
- Coordination: Every phase of work requires daily official clearance from the Northern Railway headquarters control room.
The heavy lifting, involving large cranes and specialized machinery, proceeds only after the necessary safety permissions are granted, ensuring that the construction does not compromise the integrity of existing rail operations.
Commitment to Safety and Speed
Balwan Meena, the Station Superintendent of Rohtak Junction, has confirmed that the development of the foot overbridge is being carried out in strict adherence to all safety protocols. With the work now picking up pace, the new structure is expected to be completed soon, marking a significant milestone in the modernization of Rohtak's railway facilities.