NWR Completes Samdari-Bhildi Track Renewal

North Western Railway completes a 220km track renewal on the Samdari-Bhildi section to boost heavy freight and train speeds.

Kush Singh10 November 20262 min read0 viewsDevelopment
NWR Completes Samdari-Bhildi Track Renewal

The Jodhpur Division of North Western Railway (NWR) has successfully concluded a massive 220-kilometer Samdari-Bhildi track renewal project. This extensive infrastructure overhaul, which was executed over a period of 19 months following its formal approval in March 2025, is set to significantly enhance both freight capacity and passenger speed in the region.

Upgrading for Heavy Freight and Double-Stack Containers

A major highlight of the project was the technical upgrade of the rails. The existing 52 kg rails were replaced with heavy-duty 60 kg rails. This specific configuration is designed to support high-capacity heavy freight operations, including CC+8+2T double-stack container trains.

HelloRail की हर खबर सबसे पहलेJoin Channel

Infrastructure Overhaul and High Track Quality

Beyond the rails, the project involved a comprehensive renovation of critical infrastructure components:

  • Bridge Renovations: Eight girder bridges were renovated, featuring reinforced approaches and specialized bridge channel sleepers.
  • Sleeper Replacement: Approximately 4,000 casual sleepers were replaced to ensure long-term stability.
  • Station Yard Upgrades: Turnouts and sleepers were upgraded across 16 different station yards.

As a result of these improvements, the section has achieved a Track Quality Index (TQI) of 106.20, which ranks among the highest within the entire Indian Railways network.

Boosting Train Speeds and Future Targets

Operational efficiency is already seeing a measurable boost. On a 100-kilometer portion of the route, maximum speeds have been increased from 100 km/h to 110 km/h. Railway authorities have set a target to achieve similar speed enhancements for the remaining 120-kilometer stretch by December 2026.

Additionally, the renovation of turnouts and switches in the final 12 station yards is scheduled for completion by February 2027.

Distinction from the Doubling Project

It is important to note that this track renewal project is entirely separate from the ongoing Luni-Samdari-Bhildi doubling project. The latter is a distinct initiative with a budget exceeding ₹3,530 crore and is slated for completion by July 2027.