Sitamarhi Railway Over Bridge: Construction speeds up at Mehsoul, check completion date

Kush Singh7 July 20262 min read1 viewDevelopment
Sitamarhi Railway Over Bridge: Construction speeds up at Mehsoul, check completion date

The construction of the Mehsoul Railway Over Bridge (ROB) in Sitamarhi has gained momentum. Heavy cranes are now being used to install iron slabs and girders to complete the structure. This bridge is a vital link for passengers traveling from Nepal, Darbhanga, Madhubani, and other nearby areas.

🗞️: Amrit Bharat Station Scheme: Inauguration preparations begin for Shamli and Modinagar railway stations

When will the Sitamarhi ROB be ready for public use?

HelloRail की हर खबर सबसे पहलेJoin Channel

Railway officials aim to finish their portion of the work by August 2026. The Bihar State Bridge Construction Corporation Limited has stated that the remaining work, including three spans on the Sonbarsa end, will be completed by November 30, 2026. A 62-meter long arched girder is being prepared and is expected to be launched by August 15, 2026.

What is the cost and funding of this project?

The total estimated cost of the project has reached between 86 crore and 120 crore rupees. For the approach roads, a revised estimate of 110.42 crore rupees has been made. The project follows a 50:50 cost-sharing model between the Indian Railways (Central Government) and the Bihar Government.

Why is there a delay in the approach road construction?

Engineers from the Bihar State Bridge Construction Corporation mentioned that some parts of the approach road are paused because the Railway needs open space to assemble girders and operate cranes. Additionally, former MLA Mithilesh Kumar has requested the state government to approve an additional 20 crore rupees for the approach road to avoid further delays.

Entity Responsibility Target Date
Indian Railways Bridge Construction August 31, 2026
Bihar Bridge Corp Approach Roads & Spans November 30, 2026

Frequently Asked Questions (FAQs)

सीतामढ़ी मेहसौल रेलवे ओवरब्रिज कब तक पूरा होगा?

रेलवे अपना काम अगस्त 2026 तक पूरा करेगा, जबकि बिहार सरकार नवंबर 30, 2026 तक पूरे प्रोजेक्ट को चालू करने का लक्ष्य रख रही है।

इस प्रोजेक्ट की कुल लागत कितनी है?

मुख्य निर्माण की लागत 86 से 120 करोड़ रुपये के बीच है और एप्रोच रोड के लिए संशोधित लागत 110.42 करोड़ रुपये है।