SC Orders Railways to Fix Station Amenities Nationwide
The Supreme Court mandates the Ministry of Railways to address critical infrastructure gaps and water quality issues at stations across India.

In a landmark decision for millions of commuters, the Supreme Court of India has directed the Ministry of Railways to immediately address the severe lack of basic passenger amenities at railway stations across the country. The court's directive aims to rectify systemic infrastructure deficiencies that have left travelers struggling with inadequate facilities.
The judicial intervention follows a Public Interest Litigation (PIL) filed by Krishnakant, an advocate based in Haridwar, under Article 32 of the Constitution. The case was built upon the findings of the CAG Audit Report No. 31 of 2026, which provided a grim picture of the current state of railway infrastructure.
Shocking CAG Audit Findings
The audit conducted a comprehensive survey of 512 non-suburban railway stations across 16 different railway zones. The results revealed a massive gap between prescribed standards and the reality on the ground:
- Widespread Deficiencies: Over 89 percent of the surveyed stations—totaling 458 locations—lacked one or more essential amenities.
- Minimal Compliance: Only 54 stations out of the entire survey group were found to meet all prescribed minimum standards.
- Missing Infrastructure: The report highlighted a critical absence of functional toilets, platform shelters, adequate seating, and proper signage.
Critical Concerns Over Water and Medical Care
Beyond basic comfort, the audit raised serious alarms regarding passenger health and safety. Water quality emerged as a major concern, with 436 stations lacking the necessary multi-parameter testing kits to ensure safe drinking water. Most alarmingly, the report noted that E. Coli bacteria were detected in water samples at several locations. Additionally, 78 stations failed to perform essential residual chlorine testing.
Medical preparedness also appears to be severely lacking. The CAG report found that 441 stations did not have designated medical rooms or even basic medical boxes available. In the most severe instances, 15 stations were reported to have entirely non-functional toilets, posing significant hygiene risks.
Budget Mismanagement and Project Delays
The audit did not just highlight physical shortcomings but also uncovered significant administrative and financial failures within the Ministry. Between the 2019-20 and 2023-24 financial years, the report noted that between 36% and 44% of the budget specifically allocated for passenger amenities went unspent every year.
This lack of fund utilization has led to massive delays in infrastructure development. According to the findings, 59 percent of scheduled amenity projects faced delays, while only 41 percent were completed within their designated timelines.
The Mandate for Improvement
While Railway Minister Ashwini Vaishnaw had previously initiated the 'Tank to Tap' filtration and monitoring project—aiming to cover approximately 20,000 locations—the Supreme Court has now cemented the requirement for improvements as a binding directive. The court has disposed of the PIL with the instruction that the Ministry must implement the CAG's recommendations and establish strict, station-wise timelines and action plans to bridge these critical gaps.