Rajasthan Rail Project: Udaipur to get 24.78 km double track and new tunnel

Kush Singh14 June 20262 min read0 viewsDevelopment
Rajasthan Rail Project: Udaipur to get 24.78 km double track and new tunnel

Indian Railways is upgrading the rail network in Rajasthan with a new project worth ₹467 crore. The project focuses on doubling the rail line in Udaipur to improve train movement and reduce delays. The North Western Railway has already started the land acquisition process for this work.

🗞️: Harsoli Railway Crossing 86: Reports of 10-hour closure for commuters

What are the main features of the Udaipur rail project?

HelloRail की हर खबर सबसे पहलेJoin Channel

The project involves doubling the 24.78 km rail section between Umarda and Debari. A key part of this work is the construction of a new 550-meter long tunnel near Ghatawali Mata Temple, which will run parallel to the existing one. The railway board and ministry gave their approvals in late 2025, and the goal is to finish the doubling work within three years.

How will this project benefit passengers and freight?

Feature Benefit
Double Track Trains will not have to wait at outers for crossing
New Tunnel Smoother movement in hilly terrain
Capacity Higher number of passenger and goods trains can run
Punctuality Better timing for trains coming to and from Udaipur
Infrastructure New platform and yard planned at Udaipur City station

The plan also includes moving the yard and pit line to Umarda to give more flexibility in train maintenance. These changes will help Udaipur grow as a bigger hub for trade and tourism.

What is the current status of land acquisition?

The Central Government has issued an official notification in the gazette for land acquisition. People affected by this process can submit their written objections to the District Collector’s office within 30 days of the notification. This process was formally initiated around June 11 and 12, 2026.

Frequently Asked Questions (FAQs)

उदयपुर रेल परियोजना की कुल लागत कितनी है?

इस परियोजना की अनुमानित लागत ₹467 करोड़ है, जिसमें ट्रैक दोहरीकरण और नई टनल का निर्माण शामिल है।

नया रेलवे ट्रैक कहाँ से कहाँ तक बिछाया जाएगा?

उदयपुर में उमरड़ा से देबारी के बीच 24.78 किलोमीटर लंबे रेल मार्ग का दोहरीकरण किया जाएगा।