Una Relief: ₹19.43 Cr Malahat Railway Underpass Finally Completed

The Malahat Underpass in Una has been officially completed and handed over to the public, marking the end of a significant infrastructure project for the region.
Eliminating the 10-Kilometer Detour
For local residents, the completion of this underpass brings immediate and substantial relief. Previously, whenever the railway crossing was closed, commuters were forced to take a lengthy 10-kilometer detour to reach their destinations. This new passage eliminates that inconvenience, streamlining travel for everyone in the area.
Surprise Inspection and Quality Assurance
To ensure the facility was built to the highest standards, Sadar MLA Satpal Singh Satti conducted a surprise inspection of the site. During his visit, he personally assessed the quality of the construction and the availability of public amenities provided for commuters.
MLA Satti credited Prime Minister Narendra Modi for the successful realization of the project, noting the significant impact it will have on the local community.
Project Funding and Collaboration
The project was a massive undertaking, constructed at a total cost of approximately ₹19.43 crore. The funding for this infrastructure was approved and provided by the Central Government. The successful execution of the work required close collaboration between the National Highway Authority and the Railway Department.
Key Project Milestones
- Project Commencement: October 2024
- PWD Inspection: September 2025 (conducted by Secretary Abhishek Jain)
- Target Deadline: December 31, 2025
- Final Construction Stages: February 2026
- Full Completion: September 2026
The project was specifically designed to mitigate heavy