Unnao ROB Update: Saraiya Railway Crossing overbridge expected to be completed by July 15 2026

Kush Singh4 May 20262 min read1 viewDevelopment
Unnao ROB Update: Saraiya Railway Crossing overbridge expected to be completed by July 15 2026

The construction of the Railway Overbridge (ROB) at Saraiya Railway Crossing in Shuklaganj, Unnao is currently underway. While the State Bridge Corporation has completed a major portion of the work, delays from the railway department have pushed the expected completion date to July 15, 2026.

What is the current status of the construction work

The State Bridge Corporation has finished nearly 90% of its assigned work. Only the installation of railings and painting tasks are remaining. However, the railway department, which holds a 30% share in the project, has been slow in its progress. This delay has caused frustration among local residents who face daily traffic jams.

HelloRail की हर खबर सबसे पहलेJoin Channel

Why is the project deadline being extended

The project was originally planned to open in June 2026, but technical hurdles regarding track blocks have caused delays. Ashish Verma, Deputy Chief Engineer of Northern Railway, stated that the request for a block in May 2026 was not granted. A new request for June 2026 has been submitted, with work expected to run from May 30 to July 15.

Key project details and timelines

Detail Information
Expected Completion July 15, 2026
Bridge Corporation Progress 90% Completed
Railway Department Progress 30% Work Pending
Upcoming Block Period May 30 to June 2026
Government Deadline End of 2026

Frequently Asked Questions (FAQs)

When will the Saraiya ROB be open for the public?

The overbridge is now expected to be completed and open by July 15, 2026, following the railway block in June.

How will train services be affected during the final work?

To avoid major disruptions, the railway will take round-up blocks of three hours each, affecting both up and down lines.

{“@context”: “https://schema.org”, “@type”: “FAQPage”, “mainEntity”: [{“@type”: “Question”, “name”: “When will the Saraiya ROB be open for the public?”, “acceptedAnswer”: {“@type”: “Answer”, “text”: “The overbridge is now expected to be completed and open by July 15, 2026, following the railway block in June.”}}, {“@type”: “Question”, “name”: “How will train services be affected during the final work?”, “acceptedAnswer”: {“@type”: “Answer”, “text”: “To avoid major disruptions, the railway will take round-up blocks of three hours each, affecting both up and down lines.”}}]}