The Railway Board has given its approval to run trains on the 15 kilometer section between Ghatoli and Nayagaonpura. This move is part of the larger Ramganjmandi-Bhopal rail line project. The development aims to improve connectivity in the Jhalawar district and link it better with Madhya Pradesh.
ℹ️: Mohali Railway Update: Dhakoli crossing to remain closed for emergency repair work from June 23।
What is the current status of the track?
The 22 kilometer long track from Ghatoli to Khilchipur was ready by August 2025. The Commissioner of Railway Safety (CRS) inspected the Nayagaon to Khilchipur section on 20 February 2025 and declared it fit for use. During this inspection, a trial run was successfully conducted at a speed of 130 kmph.
Key details of the rail project
- Total Distance: 22 km from Ghatoli to Khilchipur.
- Key Inspection Date: 20 February 2025 by CRS.
- Current Service: MEMU train service from Kota to Ghatoli started on 14 January 2025.
- Inauguration: The Ghatoli station was formally inaugurated on 12 March 2024.
Who are the agencies involved in this operation?
The Railway Board acted as the approving authority for the train operations. The Commissioner of Railway Safety (CRS) provided the necessary safety certification after the track inspection. The Kota Railway Division is responsible for the actual operation of the trains on this route.
Frequently Asked Questions (FAQs)
घाटोली से नयागांवपुरा ट्रैक की क्या स्थिति है?
इस खंड का निरीक्षण 20 फरवरी 2025 को CRS द्वारा किया गया और इसे ओके घोषित किया गया। ट्रैक पर 130 किमी प्रति घंटे की रफ्तार से ट्रायल भी पूरा हो चुका है।
क्या कोटा से घाटोली तक ट्रेन चल रही है?
हाँ, कोटा से घाटोली स्टेशन तक MEMU ट्रेन सेवा 14 जनवरी 2025 से शुरू हो चुकी है।