Northern Railway General Manager Rajesh Kumar Pandey visited the Lucknow-Barabanki rail section on Monday, June 22, 2026. He inspected Charbagh, Malhaur, and Barabanki stations to check the progress of ongoing development projects. The GM told officials to speed up construction and maintain high quality to ensure projects are finished on time.
🚨: Bhopal-Dhanbad Express: Route changed for selected dates, check updated timings and path।
What updates were given for Charbagh and other stations?
The General Manager reviewed the redevelopment work at Charbagh Station, which is being handled by the Rail Land Development Authority (RLDA). At Malhaur and Barabanki stations, he checked the progress of passenger facilities being built under the Amrit Bharat Station Scheme. He stated that providing modern facilities to passengers is the top priority for the railways.
What is the status of track safety and new lines?
A window trailing inspection was conducted on the Lucknow-Barabanki section to verify rail track safety. To reduce traffic and increase train speed, several quadrupling projects are underway. The key highlights of these infrastructure updates are as follows:
| Project Section | Target Completion/Status |
|---|---|
| Malhaur-Barabanki Quadrupling | August 2026 |
| Barabanki-Malhaur Section | September 2026 |
| Chhapra to Barabanki (4th Line) | DPR Approved |
Frequently Asked Questions (FAQs)
What is the target date for the Malhaur-Barabanki quadrupling project?
The Malhaur-Barabanki quadrupling project, which aims to decongest the high-traffic corridor, is targeted for completion by August 2026.
Which scheme is being used to develop Malhaur and Barabanki stations?
The development works and passenger facilities at Malhaur and Barabanki stations are being carried out under the Amrit Bharat Station Scheme.