The Indore-Dahod rail project is moving toward completion as the critical Tihi Tunnel reaches its final phase. The 2.9 km long tunnel, which was the biggest hurdle for the project, now has only a small section of work remaining. Indian Railways is working to start train operations from Indore to Dhar shortly.
👉: New Train Announcement: Indian Railways to launch Amrit Bharat Version 3.0 on Ranchi-Ajmer route।
What is the current status of Tihi Tunnel and Dhar station
The civil work of the Tihi Tunnel was completed before January 2026. Track laying inside the tunnel is finished, and work on signaling, cables, and electrification is happening. At Dhar Railway Station, the 4th platform is now ready. Officials from the Ratlam Division confirmed that the tunnel finishing work was progressing rapidly to meet the operational deadlines.
Key timelines and testing for the project
Track testing on the Pithampur-Dhar section took place from March 23 to March 26, 2026, using a tower wagon to check safety. While the overall project completion date is February 28, 2027, train services up to Dhar were anticipated by March 2026. The project aims to connect the Pithampur industrial area directly to Mumbai for easier goods transport.
| Feature | Details |
|---|---|
| Tunnel Length | 2.9 km |
| Total Project Length | 204.76 km |
| Operational Sections | Indore-Tihi (21 km) and Dahod-Katwara (11.30 km) |
| Overall Deadline | February 28, 2027 |
| Testing Period | March 23-26, 2026 |
Frequently Asked Questions (FAQs)
When will trains start running from Indore to Dhar?
Railway officials aimed to start train services between Indore and Dhar by March 2026, following the completion of the Tihi Tunnel and track testing.
What is the total length and deadline of the Indore-Dahod project?
The total length of the new rail line is 204.76 km, and the revised target date for full project completion is February 28, 2027.