This article discusses the disruption in train services in Bhagalpur due to maintenance issues with the Vande Bharat rake.
In Bhagalpur, there’s a problem caused by railway engineers’ mistakes. They are currently breaking down a maintenance pit line that was created for the Vande Bharat rake.
To fix this issue, the railway has decided to stop train services from September 5 to September 28. This means no trains will run on the affected lines during this time.
This disruption will impact many passengers who rely on these train services. People should plan their travel accordingly and find alternative transport options until the services resume.
The pit line was created recently at a cost of around 32 crores. However, engineers discovered that the design was faulty, with a sharp turn that caused problems for the train wheels.
Now, the railway is working to correct the mistake by dismantling a portion of the pit line. They aim to fix the curve issue and ensure that trains can operate smoothly in the future.
Summary:
- Train services in Bhagalpur are halted due to maintenance issues.
- The stoppage is from September 5 to September 28.
- Passengers are advised to find alternative transport during this period.
- The pit line was recently built but found to be faulty.
- Railway workers are dismantling part of the pit line to fix the design issue.