Bahraich-Jarwal Road Railway Line: RTI reveals delay in land acquisition proposal

Kush Singh7 June 20262 min read0 viewsDevelopment
Bahraich-Jarwal Road Railway Line: RTI reveals delay in land acquisition proposal

A recent Right to Information (RTI) query has brought a surprising fact to light regarding the Bahraich-Jarwal Road railway line. Despite high-level meetings and official claims, the proposal for land acquisition has not yet reached the Special Land Acquisition Officer’s office in Bahraich. This delay comes at a time when the region is expecting rapid railway expansion.

📰: Railway safety boost: High-tech composite sleepers to be installed on steel girder bridges

What does the RTI disclosure say about the project?

HelloRail की हर खबर सबसे पहलेJoin Channel

Dr. Satyabhushan Singh, the convenor of the Bahraich-Jarwal Road Rail Join Campaign, filed the RTI to check the project’s progress. The Special Land Acquisition Officer explicitly stated that their office has not received any proposal for land acquisition for this specific line. This is unexpected because a meeting was held on December 15, 2025, with the District Magistrate and Railway Ministry officials to discuss the project.

Current status of Bahraich railway projects

While the Jarwal Road line faces administrative delays, other projects in the region are moving forward. The Bahraich-Khalilabad line is seeing faster progress with significant land procurement already completed. Here are the key details of the two major projects:

Project Name Approx Length Estimated Cost Current Status
Bahraich-Jarwal Road 65-70 km ₹530 crore Survey complete, DPR finalized, land proposal pending
Bahraich-Khalilabad 240 km ₹4,939.78 crore 50% land acquired, tendering ongoing

Who completed the survey for the Jarwal Road line?

The location survey for the 65-kilometer Bahraich-Jarwal Road line was carried out by M/s Skylark Designer & Engineers Private Limited, Patna. The government approved a budget of ₹162.50 lakh for this survey. Although the Union Railway Minister informed the Lok Sabha that the DPR was finalized, the RTI reveals a disconnect between the ministry’s plans and the local land acquisition office.

Frequently Asked Questions (FAQs)

What is the status of the Bahraich-Jarwal Road railway line land acquisition?

According to an RTI disclosure updated on June 8, 2026, the Special Land Acquisition Officer of Bahraich has not yet received the proposal for land acquisition for this line.

How is the Bahraich-Khalilabad railway line progressing?

This project is moving faster, with approximately 50% of land acquisition completed as of May 1, 2026, and construction preparing to start from Utraula tehsil.