The Ministry of Railways is expanding the Vande Bharat fleet with a major focus on sleeper trains for long-distance travel. A significant part of this project involves a ₹14,400 crore deal to manufacture 120 trainsets. This initiative aims to provide a more comfortable overnight travel experience for passengers across the country.
Who is manufacturing the Vande Bharat Sleeper trains?
The production is divided among several key partners to ensure a phased rollout. Kinet Railway Solutions, a joint venture between RVNL and Russia’s Transmashholding, is handling the 120 trainsets worth ₹14,400 crore, which includes maintenance for 35 years. Other contributors include BEML, ICF Chennai, and a consortium of Titagarh Rail Systems and BHEL.
What is the current status and timeline of the project?
The first Vande Bharat Sleeper Express started on the Howrah-Kamakhya route on January 17, 2026. While the government plans to induce 260 rakes in total, some timelines have shifted. RVNL Chairman Saleem Ahmad mentioned that their first prototype is now expected in December 2026, moving from the previous June 2026 target.
Key details of the Vande Bharat Sleeper rollout
| Entity | Responsibility/Update |
|---|---|
| Kinet Railway Solutions | 120 trainsets (₹14,400 crore project) |
| Titagarh & BHEL | 80 trainsets |
| Alstom | 100 aluminium body trainsets |
| BEML & ICF | Developed the first operational sleeper train |
| Ministry of Railways | Target of 260 total sleeper rakes |
Frequently Asked Questions (FAQs)
When will the RVNL prototype be launched?
RVNL Chairman Saleem Ahmad announced that the first prototype of their Vande Bharat Sleeper train is now targeted for launch in December 2026.
Which route saw the first Vande Bharat Sleeper Express?
The first Vande Bharat Sleeper Express was inaugurated by PM Narendra Modi on January 17, 2026, for the Howrah-Kamakhya route.