The construction of a 26 km long third rail line between Keetham and Bhandai is nearing completion. This project, built at an estimated cost of 600 crore rupees, aims to reduce the heavy pressure of goods trains on the New Delhi-Agra section. The work is being carried out by Rail Vikas Nigam Limited (RVNL) and is expected to be finished within a year.
👉: Mohali Railway Underpass: Groundbreaking ceremony at Baltana crossing on May 20।
How will this third line benefit passengers?
This new line will divert about 60-70% of freight trains away from the main route. As a result, the waiting time for trains at the outer signals of Agra Cantt station will decrease. More than two dozen passenger trains, including the Secunderabad Rajdhani, will see better punctuality and fewer delays.
What is the current status of the project?
The project has seen significant progress recently. A long-standing protest by farmers in Nagar village ended on May 15, 2026, after railway officials started the construction of a bridge on road number 24. Additionally, the Agra Railway Division received a budget of 1,370 crore rupees on February 4, 2026, to speed up the construction of this line and a new station.
| Project Detail | Information |
|---|---|
| Section | Keetham to Bhandai |
| Length | 26 KM |
| Cost | 600 Crore Rupees |
| Executing Agency | RVNL |
| Completion Timeline | Within one year |
| Impact | 60-70% freight trains diverted |
Frequently Asked Questions (FAQs)
Which trains will benefit from the Keetham-Bhandai third line?
More than two dozen passenger trains, including the Secunderabad Rajdhani, will benefit as freight trains are diverted, reducing waiting time at Agra Cantt.
Who is constructing the third rail line and what is the cost?
The project is being constructed by Rail Vikas Nigam Limited (RVNL) with an estimated cost of 600 crore rupees.