The Ministry of Railways has started the process to revive the old Tadighat railway station in Ghazipur. Work to clear encroachments from the British-era station premises began on Monday, May 18, 2026. This project aims to improve local connectivity and support trade in the region.
What are the key details of the revival project?
The project has an approved budget of ₹11 crore. The survey was finished by March 9, 2026, and the tender process received approval on March 11, 2026. Indian Railways expects to complete the work within four months. A new 2.5-kilometer rail line is being built to connect the old station.
How will the station operate and who will benefit?
The old station will be renamed as Old Railway Station, while the newer facility will be called New Tadighat Railway Station. The first phase will focus on building loading-unloading points and a goods blast siding. This move will benefit traders and residents of 52 villages in Ghazipur.
| Detail | Information |
|---|---|
| Budget | ₹11 Crore |
| Expected Timeline | 4 Months |
| Station Age | Approximately 147 Years |
| Beneficiaries | 52 Villages in Ghazipur |
| Primary Focus | Loading-Unloading & Goods Siding |
What is the status of the New Tadighat Station?
The new station was inaugurated by Prime Minister Narendra Modi in March 2024. However, it has faced complaints regarding cracking walls and platforms. Railway Vikas Nigam Limited (RVNL) is currently investigating these quality issues through a technical team. Requests for better passenger amenities have also been sent to higher authorities.
Frequently Asked Questions (FAQs)
What will be the focus of the first phase of the revival?
The first phase will prioritize the development of loading-unloading facilities and a goods blast siding to help local traders.
When will the project be completed?
The revival work is expected to be completed within four months following the start of encroachment removal in May 2026.