The Prayagraj Division of North Central Railway has completed a major part of the infrastructure work on the Mirzapur-Sonbhadra route. A new Road Over Bridge (ROB) has been installed to reduce traffic congestion and improve safety for commuters. These developments are part of a larger plan to enhance connectivity in the Vindhya region.
What is the update on the Road Over Bridge at Lusa?
Between June 19 and June 20, 2026, the railway team successfully installed heavy steel girders for a 585-meter long bridge. This bridge is located at level crossing number-19 near Lusa on the Chunar-Chopan section. It will help remove long traffic jams on State Highway-35, making travel smoother for both trains and road vehicles. The project was led by DRM Rajneesh Agarwal along with engineers IPS Yadav and Lal Bahadur.
What are the details of the rail doubling and expressway projects?
The Chunar-Chopan rail line is being doubled to increase train capacity. This 102-kilometer project received central cabinet approval in August 2023 with a budget of 1424 crore rupees. It includes a 1128-meter bridge over the Son River and is expected to be finished by 2027. Additionally, the Vindhya Expressway is being built from Prayagraj to Sonbhadra via Mirzapur, with a target completion date of 2029.
Key Infrastructure Projects Overview
| Project Name | Key Detail | Target/Budget |
|---|---|---|
| Lusa ROB | 585-meter long bridge | Completed June 2026 |
| Chunar-Chopan Doubling | 102 km rail doubling | 2027 / 1424 Crore |
| Vindhya Expressway | 330 km connectivity | 2029 |
| Robertsganj-DDU Line | New rail line proposal | Survey submitted |
Frequently Asked Questions (FAQs)
What is the benefit of the new bridge at Lusa?
The 585-meter Road Over Bridge at level crossing number-19 will eliminate traffic jams on State Highway-35, ensuring a smooth flow for both rail and road traffic.
When will the Chunar-Chopan rail doubling be completed?
The doubling of the 102-kilometer line, which includes a bridge over the Son River and a budget of 1424 crore rupees, is targeted for completion by 2027.