The Ministry of Railways approved a project worth ₹274 crore to upgrade the signaling system in the Malda Division of Eastern Railway. This project includes Bhagalpur and will replace old relay-based systems with advanced Electronic Interlocking (EI) technology. The announcement was made around July 2nd and 3rd, 2026.
What are the key details of the ₹274 crore project?
The modernization plan focuses on improving high-utilization routes to ensure smoother train movements. The project will cover a total of 20 locations across the division.
- Total Budget: ₹274 Crore
- Total Locations: 20 (18 railway stations and 2 Intermediate Block Signalling locations)
- Technology: Electronic Interlocking (EI) replacing Panel and Route Relay Interlocking
- Division: Malda Division, Eastern Railway
How will this upgrade benefit the passengers?
The new system will make train operations more reliable and efficient. It will reduce the chances of service disruptions and allow railway staff to fix faults much faster. This will lead to better punctuality of trains and overall safety for passengers. Additionally, these stations will be ready to integrate with Kavach, the indigenous train collision avoidance system.
Frequently Asked Questions (FAQs)
What is Electronic Interlocking and why is it being installed?
It is an advanced signaling technology that replaces old relay systems. It is being installed to improve train safety, increase operational efficiency, and reduce delays in the Malda Division.
Will this project help in implementing Kavach?
Yes, the new electronic interlocking systems will better equip the affected stations to integrate with Kavach, the indigenous train collision avoidance system.