Rail Vikas Nigam Limited (RVNL) has secured a significant project from the South East Central Railway. The order is valued at ₹221.33 crore and focuses on upgrading the railway signaling systems in the Bilaspur Division. The company was declared the lowest bidder (L1) for this infrastructure project on May 12, 2026.
📰: Bhopal Division Train Update: Several trains cancelled and diverted due to Pune division work।
What is the scope of this signaling project?
The project involves replacing old panel interlocking systems with modern electronic interlocking. This upgrade includes the installation of indoor and outdoor gear, construction of Optical Fiber Cable (OFC) huts, and the development of Signal and Telecommunication (S&T) service buildings along with electrification.
Which stations and timelines are involved?
The work will be carried out across several stations in the Bilaspur Division, including BSPR, KLPG, ABKP, MZH, HRV, PRDL, KTMA, BJRI, KZ, MDGR, CHRM, GTK, KLTR, PLAU, and KBS. The entire project is based on the Engineering, Procurement, and Construction (EPC) model and must be completed within 730 days.
| Detail | Information |
|---|---|
| Project Value | ₹221,33,11,931.64 |
| Executing Agency | RVNL |
| Issuing Authority | South East Central Railway |
| Completion Time | 2 Years (730 Days) |
| Project Type | EPC Model |
Frequently Asked Questions (FAQs)
RVNL को कितना बड़ा ऑर्डर मिला है?
RVNL को दक्षिण पूर्व मध्य रेलवे से ₹221.33 करोड़ का ऑर्डर मिला है, जिसके तहत बिलासपुर डिवीजन में सिग्नलिंग सिस्टम को आधुनिक बनाया जाएगा।
इस प्रोजेक्ट को पूरा करने में कितना समय लगेगा?
इस पूरे प्रोजेक्ट को पूरा करने की समय-सीमा 730 दिन यानी लगभग 2 साल तय की गई है।