The North Eastern Railway is working on the construction of a third railway line between Gonda Junction and Kachhari Railway Station. To complete this project, a 40-day mega block has been approved by the Railway Board. This work will lead to the cancellation and diversion of several trains to ensure safety and technical accuracy during the non-interlocking process.
Which trains are affected by the construction work?
The construction work has led to a significant change in train operations. According to the Lucknow Division, 40 trains will be cancelled and 53 trains will be diverted. Local DEMU services on the Gonda-Bahraich section, including train numbers 75109, 75110, 75111/75112, and 75113/75114, will remain suspended until July 10, 2026.
What is the timeline for the third line project?
The construction unit of North Eastern Railway started the remaining work on June 10. The mega block for non-interlocking is in effect from June 10 to July 9. Mahesh Gupta, PRO of Lucknow Division, stated that about five kilometers of track work is being completed. The Commissioner of Railway Safety (CRS) will inspect the new section on July 10, after which normal services will resume.
| Detail | Information |
|---|---|
| Work Area | Gonda Junction to Kachhari Station |
| Cancellation Period | June 21/22 to July 10, 2026 |
| Total Cancelled Trains | 40 Trains |
| Total Diverted Trains | 53 Trains |
| CRS Inspection Date | July 10, 2026 |
Frequently Asked Questions (FAQs)
How long will the trains be cancelled in Gonda?
Trains are cancelled starting from June 21/22, 2026, until July 10, 2026, due to the construction of the third rail line.
Which specific local trains are suspended on the Bahraich route?
DEMU trains 75109, 75110, 75111/75112, and 75113/75114 on the Gonda-Bahraich section are suspended until July 10.