The doubling of the Phaphamau bypass rail line is gaining momentum to improve train connectivity in the Prayagraj region. As part of this expansion, the administration is moving forward with land acquisition, which includes 10,225 square meters of land across four villages in Prayagraj. This move aims to reduce congestion and ensure smoother train movements.
ℹ️: Railway Board to implement major reforms in wagon design policy to boost freight efficiency।
What are the key details of the Phaphamau-Unchahar doubling project?
The Railway Board has approved the doubling of the 72.27 km Phaphamau-Unchahar rail line with an estimated cost of 113.08 million USD. General Manager of Northern Railway, Ashok Kumar Verma, stated that work is expected to start after Mahakumbh 2025. The project will cover Prayagraj, Pratapgarh, and Raebareli districts and is slated for completion by March 31, 2028.
Which other sections are being upgraded around Phaphamau?
Multiple sections are undergoing development to enhance the network efficiency. The Phaphamau-Unnao line, spanning about 200 km, received 1,600 crore rupees in the 2023-24 budget. Additionally, the 6 km stretch between Phaphamau and Prayag Junction is critical for removing delays caused by the single track over the Ganga river.
| Project Section | Length/Detail | Expected Timeline/Status |
|---|---|---|
| Phaphamau-Unchahar | 72.27 km | Start: April 2026, End: March 2028 |
| Phaphamau-Unnao | ~200 km | Tendering in 2026 |
| Phaphamau-Pratapgarh | Doubling | Completion by October 2026 |
| Phaphamau-Prayag Jn | 6 km | Critical for Ganga bridge bottleneck |
Frequently Asked Questions (FAQs)
When will the Phaphamau-Unchahar doubling work start?
The work is expected to begin after Mahakumbh 2025, with an official start date set for April 1, 2026.
Which districts will benefit from the Phaphamau-Unchahar project?
This project will cover and benefit the districts of Prayagraj, Pratapgarh, and Raebareli.