Indian Railways has achieved a significant milestone in Rajasthan by upgrading the 94-kilometer railway track on the Samdari-Bhildi section. This enhancement allows trains to operate at a maximum speed of 110 kmph, which is expected to save travel time for thousands of daily passengers. The upgrade focuses on strengthening the infrastructure to ensure a smoother and faster journey across western Rajasthan as part of a larger regional connectivity plan.
What are the key details of the Luni-Samdari-Bhildi doubling project?
The doubling of the 271.97 km Luni-Samdari-Bhildi rail line was approved with a budget of 3530 crore. This project is vital for improving connectivity between Rajasthan and Gujarat, supporting both passenger and freight movement. The overall project is scheduled for completion by the end of 2027, with specific sections expected to be ready much sooner.
- Budget Allocation: 3530 crore allocated for the entire double line project
- Completion Target: Entire corridor planned for operation by late 2027
- Current Milestone: 94 km of track work completed with increased speed limits
- Upcoming Goal: Additional 29 km of track doubling targeted by March
How is technology used to monitor the construction progress?
To ensure timely execution and maintain high safety standards, North Western Railway has introduced drone-based monitoring for the project. A contract worth 30.7 million was awarded to Matrix Geo Solutions for this purpose, covering the entire 271.97 km corridor. This technology helps in tracking construction progress systematically without requiring frequent manual inspections at every site.
| Feature | Project Impact |
|---|---|
| Drone Monitoring | Reduces physical site inspections by nearly 50 percent |
| Reporting Speed | Shortens progress reporting timelines by 25 percent |
| Modern Infrastructure | Uses 60 kg rails and wider concrete sleepers for higher stability |