The doubling and electrification project of the Bhatni-Aundihar rail line under North Eastern Railway is now in its final stages. This project aims to improve rail connectivity in the Purvanchal region, reduce train delays, and allow high-speed trains to run. The work is being carried out at a total cost of ₹1177.96 crore.
🗞️: Kanpur Railway Project: Elevated track construction to start between Anwarganj and Mandhana।
What is the current status and timeline of the project?
The doubling work from Varanasi to Belthara Road is expected to finish by the end of May 2026. After this, the Belthara Road-Bhatni section will be prioritized for completion within the next three months. The overall Bhatni-Aundihar project, including the remaining work between Lar Road and Belthara Road, is targeted for completion by September 2026.
Key details of the Saryu River bridge and high-speed trials
A new 1.08 km long double-line rail bridge is being built over the Saryu (Ghaghra) river at Turtipar, which is expected to be ready by July 2026. This bridge was constructed by SP Singla Constructions. Additionally, successful high-speed trials were conducted by the Commissioner of Railway Safety (CRS) on the Pivkol-Lar Road section in March 2026, reaching a maximum speed of 127 kmph.
Project details and expected impact
| Feature | Details |
|---|---|
| Total Cost | ₹1177.96 Crore |
| Executing Agency | North Eastern Railway |
| Turtipar Bridge Length | 1.08 Kilometers |
| Completed Track | Over 89 Kilometers |
| Remaining Section | Last 13 km of Salempur-Belthara Road |
Railway officials stated that once the double line is ready, there will be better control over train delays and average speeds will increase. This will improve connectivity between Varanasi, Deoria, and Gorakhpur. The new infrastructure is also designed to safely handle high-speed trains like the Vande Bharat Express.
Frequently Asked Questions (FAQs)
When will the Belthara Road-Lar Road doubling work be completed?
The entire Bhatni-Aundihar doubling project, including the Lar Road to Belthara Road section, is targeted for completion by September 2026.
What is the status of the new bridge over the Saryu river?
The 1.08 km long double-line rail bridge at Turtipar is expected to be ready by July 2026.