A major milestone was achieved in the Panna district as the first 12-coach trial train successfully reached Devendranagar station on Wednesday, June 10, 2026. This trial run ended a long wait for the local residents. The event saw a massive gathering of people who welcomed the train with great enthusiasm.
How was the trial run conducted
Commissioner of Railway Safety (CRS) Guru Prakash led the inspection and speed trial of the new 7-kilometer track between Phulwari and Devendranagar. The special train left Satna at 8:00 AM and reached Phulwari by 9:00 AM. After the inspection started at 9:30 AM, the train finally arrived at Devendranagar by 2:00 PM. Senior officials including DRM Kamal Kumar Talreja and CAO M.S. Hashmi were present during the process.
What is the future plan for the Panna rail line
Railway Executive Engineer P.K. Singh confirmed the success of the trial. The railway department now plans to extend the track work toward Sakariya. The CRS trials for the Sakariya section are expected by October 2026 after the monsoon season. Work on a 350-meter underground tunnel in Sakariya is already 80% complete.
Project details and expected completion
| Project Detail | Information |
|---|---|
| Total Satna-Panna Line Length | 73.55 km |
| Larger Project Scope | 541 km (Lalitpur-Satna-Rewa-Singrauli-Khajuraho-Mahoba) |
| Expected Completion Date | March 2027 |
| Key Benefit | Boost to trade, tourism, and connectivity |
Frequently Asked Questions (FAQs)
When will the full Satna-Panna rail line be completed?
The entire 73.55-kilometer Satna-Panna new rail line project is expected to be completed by March 2027.
What is the status of the Sakariya section?
The track work is extending to Sakariya, where a 350-meter underground tunnel is 80% complete. Trials there are expected by October 2026.