The Nagpur Division of South East Central Railway (SECR) completed the construction of a new goods shed line at Rasamra station. This project was finished in record time and commissioned on June 12, 2026. The new line will help in increasing the movement of goods and support the expansion of passenger facilities at Durg station.
🚨: Railway safety boost: Indian Railways to install new fire extinguishers in 30,000 coaches।
How was the project completed in record time?
The railway team executed the work through a very tight schedule between June 9 and June 12, 2026. The technical process was divided into two main phases to ensure minimal disruption to train traffic.
- Pre-non interlocking: 10 points and crossings were installed and 2 were removed during a short 6-hour traffic block.
- Non-interlocking: The final stage of the work was completed in just 12 hours.
Who were the key contributors to this achievement?
The project was a result of coordination between several railway departments. DRM Deepak Kumar Gupta congratulated the teams for their hard work and technical skill.
| Entity/Department | Role/Contribution |
|---|---|
| SECR Nagpur Division | Overall execution and management |
| Gati Shakti Unit Nagpur | Project planning and speed implementation |
| S&T Department | Signaling and Telecommunication work |
| Electrical Project | Power and electrical infrastructure |
Frequently Asked Questions (FAQs)
What are the benefits of the new goods shed line at Rasamra?
The new line will increase the freight loading and unloading capacity of the region. It will also help in speeding up the expansion of passenger amenities at the nearby Durg station.
When was the project commissioned?
The project was successfully completed and commissioned on June 12, 2026, after a series of fast-tracked interlocking works.