The old railway over bridge (ROB) located in front of the Allahabad High Court in Prayagraj is being demolished to make way for a new structure. The State Bridge Corporation has received approval for the new design, and the demolition of the old bridge has already started. This project aims to improve connectivity and safety for commuters in the area.
ℹ: Dalmianagar Railway Project: 430 crore rupees approved for new wagon repair factory in Rohtas।
What are the key details of the new ROB construction?
The new bridge will be 600 meters long and will be built on a pile foundation with 14 pillars. The distance between the pillars will vary between 12 and 24 meters. The State Bridge Corporation will handle 540 meters of the construction, while the North Central Railway (NCR) will manage the remaining 60 meters. The project is expected to be completed within 1.5 years of the start of actual construction.
What is the budget and timeline for the project?
| Detail | Information |
|---|---|
| Total Project Cost | 51.50 Crore Rupees |
| First Installment Released | 11.58 Crore Rupees |
| Bridge Closure Date | 10 April 2026 |
| Target Completion Date | May 2028 |
| Demolition Period | Approximately 2 months |
The old bridge was declared dilapidated by the PWD in 2024, leading to a ban on four-wheelers in November 2024. By April 2026, it was completely closed for all traffic, including two-wheelers. Current work involves removing railings, and the main structure will be demolished using JCBs shortly.
Frequently Asked Questions (FAQs)
How long will it take to complete the new Prayagraj ROB?
The actual construction is expected to take about 1.5 years, with a final completion target set for May 2028.
Who is responsible for the construction of the new bridge?
The State Bridge Corporation is responsible for 540 meters of the bridge, and the North Central Railway (NCR) is responsible for the remaining 60 meters.