The construction of the new rail line between Neura and Jatdumri is now complete. This 18.2 to 19 kilometer stretch is part of a larger project connecting Neura, Daniyawan, Biharsharif, Barbigha, and Sheikhpura. The project is being executed by Rail Vikas Nigam Limited (RVNL) under the Danapur Division of East Central Railway.
When will trains start running on the Neura-Jatdumri line?
The Commissioner of Railway Safety (CRS) team is expected to inspect the line in May 2026. If the inspection is successful, the NoC for train operations could be issued by the first week of June 2026. Regular train services are expected to begin within six months after the approval, starting with goods trains followed by passenger trials.
What are the key features and benefits of this new line?
This new line will reduce the traffic pressure on the Patna-Kiul route and provide better connectivity to several areas. New stations and halts have been developed along this stretch to benefit local passengers.
| Feature | Details |
|---|---|
| Total Length | 18.2 km to 19 km |
| Electrification | 95% Completed |
| Executing Agency | RVNL |
| New Stations/Halts | Gompura, Bagipur, Nachawa, Biju Bigha, Fazalchak, Gauspur, Sarathua |
| Main Junction | Jatdumri Junction (being developed as a major hub) |
What is the current status of the work?
Most of the construction work is finished, and electrification is nearly complete. Non-interlocking (NI) work near Neura station was recently carried out to ensure proper connectivity. Railway officials stated that the route will be opened for traffic only after the final clearance from the Railway Safety Commissioner.
Frequently Asked Questions (FAQs)
नेउरा-जटडुमरी रेल लाइन की लंबाई कितनी है?
इस नई रेल लाइन की कुल लंबाई लगभग 18.2 किलोमीटर से 19 किलोमीटर के बीच है।
इस लाइन से किन स्टेशनों को फायदा होगा?
इससे गोंपुरा, बागीपुर, नाचावा, बीजू बीघा, फजलचक, गौसपुर और सरथुआ जैसे नए स्टेशनों को कनेक्टिविटी मिलेगी।