The redevelopment of Pilibhit Railway Station under the Amrit Bharat Station Scheme is moving slowly. While the project aims to modernize the station with a budget of 16.74 crore rupees, passengers continue to face a shortage of basic facilities. The project was part of a larger national plan launched in February 2023 to upgrade 1275 stations across India.
What is the current status of work at Pilibhit Station?
Recent updates show that a lift service started on June 26, 2026, which has helped elderly passengers and children. Work on escalators has also begun and trials are expected soon. However, most of the major goals set for December 2025 remain incomplete. General Manager of North Eastern Railway, Atul Borwankar, previously expressed dissatisfaction with the slow pace of work during an inspection.
Which facilities are still pending for passengers?
Despite the budget and time elapsed, several critical infrastructure tasks are still on the to-do list. The following table outlines the current progress:
| Completed/Started | Pending/Incomplete |
|---|---|
| Lift Service | Escalator Trials |
| Initial Planning | Circulating Area Expansion |
| Budget Allocation | Two New Railway Lines |
| – | Station Building Facelift |
| – | Drainage System |
| – | RO Water & Fan Installation |
Senior Divisional Commercial Manager Sanjeev Sharma stated that monitoring reports are being shared regularly to speed up the process. He mentioned that the station will also feature ‘Bansuri’ murals to represent the local identity of the district.
Frequently Asked Questions (FAQs)
What is the total budget for Pilibhit station redevelopment?
The redevelopment of Pilibhit Railway Station is being carried out at a total cost of 16.74 crore rupees under the Amrit Bharat Station Scheme.
When is the work expected to be completed?
The target for completing most of the work was December 2025, and officials are now working to speed up the remaining tasks.