The North Eastern Railway is introducing an Artificial Intelligence (AI) system to monitor traffic at railway crossings in the Lucknow division. This new technology will replace the old manual method of counting vehicles to ensure better accuracy. The data collected by these AI cameras will be used to decide where new underpasses or overbridges are needed most.
How will the AI system work for traffic monitoring?
Previously, railway staff counted vehicles manually over seven days every three years, which was often inaccurate. Now, AI cameras will automatically count two-wheelers and four-wheelers passing through the crossings. As a pilot project, 21 railway crossings in the Lucknow division have been selected for this installation. The administration is prioritizing spots where the three-year manual counting cycle is ending.
What are the rules for building overbridges or underpasses?
The decision to build a bridge depends on the Train Vehicle Unit (TVU) calculation. The cost of these projects is shared equally between the railway and the state government. The specific requirements are as follows:
| TVU Count | Action/Priority |
|---|---|
| Over 1 Lakh | Proposal for underpass or overbridge can be initiated |
| 5 Lakh or more | High priority for project construction |
Frequently Asked Questions (FAQs)
How many crossings will get AI cameras in the pilot project?
A total of 21 railway crossings within the Lucknow division of the North Eastern Railway have been selected for the installation of AI-based cameras.
What is the TVU limit for starting a bridge proposal?
A proposal for an underpass or overbridge can be initiated if the Train Vehicle Unit (TVU) exceeds one lakh, while those with five lakh TVU get priority.