Railway and PWD engineers are working on a war footing to complete the Kali Mori Underpass in Alwar, Rajasthan. A 10-hour railway block was implemented on May 10, 2026, from 10 AM to 8 PM to fit concrete boxes. This project aims to connect the main city with the Patri Paar area, benefiting thousands of local residents.
🚨: Kanpur Ganga Railway Bridge: Train services to resume from May 14 after 42-day block।
What is the impact on train services and local areas?
To facilitate the construction, 11 trains have been diverted. This includes several express and Vande Bharat services running between cities like Delhi Cantt, Jodhpur, Jammu Tawi, and Udaipur City. Additionally, electricity supply remained shut from 8 AM to 8:30 PM in areas including Moti Nagar, Heerabas, and Station Road. Bus routes via Kali Mori were also diverted to avoid traffic congestion.
What are the project details and benefits for locals?
The underpass will significantly reduce travel distance for residents of Alka Puri, Bank Colony, and Friends Colony from 2 kilometers to just 200 meters. The structure is 3 meters deep, 5 meters wide, and 16 meters long. The project cost has increased to approximately 5 crore rupees. Pre-made cement blocks and iron gutters are being used to speed up the process.
| Feature | Details |
|---|---|
| Expected Completion | June 2026 |
| Construction Method | Pre-made concrete boxes |
| Total Cost | Around 5 Crore Rupees |
| Travel Reduction | 2 km to 200 meters |
| Workforce | Over 100 laborers and 15-20 machines |
Frequently Asked Questions (FAQs)
When will the Kali Mori Underpass be fully operational?
The underpass is expected to be fully operational by June 2026, with contractor Sandeep Chaudhary stating it may take 2 to 3 months.
Which trains were affected by the construction block on May 10?
11 trains, including Vande Bharat and express services between Bhuj, Delhi Cantt, Jodhpur, and Jammu Tawi, were diverted.