Indian Railways is working to start the Bijwasan Railway Terminal by October 2026. This new terminal will help reduce the heavy load on New Delhi and Sarai Rohilla stations. The move comes as the redevelopment work of New Delhi Railway Station is currently underway.
What are the key features of Bijwasan Terminal
The new terminal will be built with modern facilities similar to an airport. It will have eight platforms and separate areas for arrival and departure. The station will provide easy connectivity via road, metro, and a proposed inter-state bus terminal, being close to Indira Gandhi International Airport and Dwarka Sector 21 Metro Station.
How will this affect train operations
More than 50 trains will be shifted from New Delhi station to Bijwasan. This will be especially beneficial for trains heading towards Mumbai, Jaipur, and Gurugram. While the target date is October 2026, some officials expect operations to begin before Diwali this year. The India Investment Grid has listed the completion date as December 31, 2026.
Current status of the construction work
| Aspect | Status/Detail |
|---|---|
| Project Completion | 80% work finished by March 2026 |
| Main Building | Structure almost ready |
| Tracks | Laying work in final stage |
| Signaling | System being installed |
| Management | RLDA issued tender to a private company for 9 years |
| Environmental | CEC allowed removal of 1279 trees |
Frequently Asked Questions (FAQs)
When will Bijwasan Railway Terminal start working?
The official target is October 2026, though some railway officials hope to start operations before Diwali this year.
How many trains will move to the new terminal?
More than 50 trains will be shifted from New Delhi station to Bijwasan to reduce congestion.