Indian Railways is planning a major infrastructure upgrade in Kanpur to solve the city’s traffic problems. An elevated railway track will be built between Anwarganj and Mandhana at an estimated cost of 1115 crore rupees. This project will remove 18 railway crossings, providing relief to nearly 50 to 60 lakh people who face daily traffic jams.
What are the key details of the project
The project covers a distance of approximately 15.51 km to 16.25 km. The Railway Board has already approved the construction, and the contract was awarded to Ravi Infrabuild Projects Limited for 830.90 crore rupees. The goal is to complete the entire work by October 30, 2027. Topographical survey work has already started on the ground.
How will it affect train services and stations
To facilitate construction, the railway has requested a 730-day block from the Railway Board. Once approved, train movement on the Anwarganj-Mandhana route will stop for a period. Additionally, the Rawatpur and Kalyanpur railway stations will be closed. A new elevated ‘Atal Station’ will be built near CSJMU university, which will have direct connectivity with the Metro.
What is the status of land acquisition
| Detail | Information |
|---|---|
| Total Land Required | 22,306 square meters |
| Additional Land Needed | 1,000 square meters |
| Budget Released | 35.87 crore rupees |
| Compensation Start Date | May 6, 2026 |
| Current Status | Notice to Proceed |
Frequently Asked Questions (FAQs)
Which stations will be closed due to this project?
The Rawatpur and Kalyanpur railway stations will be closed to make way for the elevated track construction.
What is the special feature of the new Atal Station?
The Atal Station will be an elevated station located near CSJMU university and will provide direct connectivity to the Metro.