The new building of Laxmi Bai Nagar Railway Station in Madhya Pradesh is nearly complete. Railway officials expect the station to start operating from the new premises within the next 15 days or by May 2026. This upgrade will significantly improve connectivity between Indore and Ujjain for passengers.
ℹ: Samastipur Railway Division: New time table and fare details to be displayed at 220 stations।
What new facilities are available at the station?
The new station building is 1.5 times larger than the old one and includes several modern amenities. The construction of a new waiting hall, ticket windows, retiring rooms, and a dedicated room for the Station Master is already finished. Additionally, a new 36-foot wide foot over bridge has been completed, and three new lifts are being installed for easier access.
Project cost and key development details
The modernization of Laxmi Bai Nagar station is being carried out by the Ratlam Division of Western Railway under the Amrit Bharat Station Scheme. The total cost and infrastructure details are as follows:
| Feature | Details |
|---|---|
| Modernization Cost | Approximately 45 Crore Rupees |
| Railway Overbridge (ROB) Cost | Approximately 10 Crore Rupees |
| Total Platforms | 3 existing, 2 under construction |
| Special Goal | Manage 300 trains during 2028 Simhastha Mela |
| Foundation Stone | Laid on 19 July 2023 |
Why was the project delayed and what is next?
The original target to complete the work was February 2026, but it was delayed due to track laying, platform construction, and train operations. Currently, the work on the first berth of Platform Number 1 is complete, and upper-level construction is moving fast. The old master building and the old foot over bridge will be demolished soon to make way for the new infrastructure.
Frequently Asked Questions (FAQs)
When will the new Laxmi Bai Nagar station building be operational?
The building is almost ready and operations are expected to start within 15 days or by May 2026.
What is the total cost of the station’s modernization?
The station is being modernized at a cost of approximately 45 crore rupees, with an additional 10 crore rupees for the Railway Overbridge.
{“@context”: “https://schema.org”, “@type”: “FAQPage”, “mainEntity”: [{“@type”: “Question”, “name”: “When will the new Laxmi Bai Nagar station building be operational?”, “acceptedAnswer”: {“@type”: “Answer”, “text”: “The building is almost ready and operations are expected to start within 15 days or by May 2026.”}}, {“@type”: “Question”, “name”: “What is the total cost of the station’s modernization?”, “acceptedAnswer”: {“@type”: “Answer”, “text”: “The station is being modernized at a cost of approximately 45 crore rupees, with an additional 10 crore rupees for the Railway Overbridge.”}}]}