Rail passengers traveling between Gorakhpur and Lucknow will face significant disruptions in June and July 2026. North Eastern Railway has announced a mega block for infrastructure upgrades, which will impact a total of 129 trains. This move is part of a larger plan to increase train speeds and reduce travel time on this busy route.
ℹ️: Buxar Bridge Update: Itadhi railway overbridge closed after cracks appear in flank section।
How will the train services be affected
The mega block has led to a major reshuffle in train operations. According to CPRO Sumit Kumar, the impact on services is as follows:
| Impact Type | Number of Trains |
|---|---|
| Cancelled Trains | 31 |
| Diverted Routes | 53 |
| Short-Terminated/Originated | 17 |
| Controlled Operation | 14 |
| Total Affected | 129 |
What are the dates and reasons for the block
A major mega block is scheduled from July 5 to July 10, 2026, on the Gorakhpur-Lucknow route. This is for pre-non interlocking and non-interlocking work to lay a third rail line between Gonda and Gonda Kacheri stations. Additionally, a traffic block is in place from Friday until June 9, 2026, between Pipraich and Unaula stations on the Narkatiaganj-Gorakhpur section for doubling work.
How can passengers check their train status
Railway administration has advised all passengers to verify their train status before starting their journey. You can check real-time updates using the NTES app, the official railway website, or the railway helpline numbers to avoid any inconvenience at the station.
Frequently Asked Questions (FAQs)
Why are trains being cancelled on the Gorakhpur-Lucknow route?
Trains are affected due to a mega block for laying a third rail line between Gonda and Gonda Kacheri and doubling work between Pipraich and Unaula stations.
Which dates are most critical for the mega block?
A major block is scheduled from July 5 to July 10, 2026, while another traffic block is active until June 9, 2026.