The construction of the new broad gauge railway line between Khalilabad and Bahraich is moving forward quickly. In the Dumariyaganj area of Siddharthnagar district, concrete sleepers were unloaded at Bhagwanpur village on Wednesday, June 17, 2026. This development marks a significant step in the track-laying process for the region.
🗞️: South Eastern Railway: New demands for Kolhan region rail development and passenger facilities।
What is the current status of the project?
The project covers a total distance of 240.26 km with an estimated cost of ₹4,940 crore. While the original target was 2024-25, the work is now expected to be completed by 2026 or 2027. Currently, soil leveling and boundary wall construction are happening at the new Bahraich-Dumariyaganj station, and earth filling is underway at Khesaraha station.
What are the key project details?
| Feature | Details |
|---|---|
| Total Length | 240.26 km |
| Estimated Cost | ₹4,940 Crore |
| Expected Completion | 2026 or 2027 |
| Executing Agency | North Eastern Railway / Ministry of Railways |
| Land Acquisition | 40-50% completed overall |
How will this benefit the local people?
MP Jagdambika Pal stated that this line will improve connectivity in the border and Terai regions of Eastern Uttar Pradesh. The project aims to link Bahraich with Khalilabad, which will help in starting small industries and creating new jobs. Additionally, a new Amrit Bharat Express service is approved to run between Delhi and Gorakhpur, passing through Siddharthnagar, Balrampur, and Gonda.
Frequently Asked Questions (FAQs)
When will the Khalilabad-Bahraich railway line be completed?
The project is now anticipated to be finished by 2026 or 2027, following the initial approval in October 2018.
What is the current land acquisition status in Dumariyaganj?
Land demarcation is in progress in 15 out of 46 designated villages, though Tehsildar Ravi Kumar Yadav confirmed no official registries are finalized yet.